Airport Projects
Airport development under way across India — cost, capacity and expected completion, from AAI's own project reports.
| Airport | State | Capacity MPPA | Cost crore | Commenced | AAI's target date |
|---|---|---|---|---|---|
| LucknowCompletedNew integrated terminal building (Chaudhary Charan Singh International Airport). | Uttar Pradesh | 13.6 | ₹1,383 | September 2018 | September 2021 |
| PatnaCompletedNew integrated terminal building; inaugurated by PM Modi on 29 May 2025, operational from 3 June 2025 (Jai Prakash Narayan Airport). | Bihar | 8 | ₹1,217 | October 2018 | October 2022 |
| SuratCompletedNew terminal building, inaugurated 17 December 2023. | Gujarat | 2.6 | ₹138 | May 2019 | October 2023 |
This tracker is kept by hand from AAI's own project reports, not by an automatic feed. A target date already in the past doesn't mean this page is stale — check the status badge next to each airport for what's actually happened.